The Mining Play - Medinah Minerals (MDMN) and Cerro Dorado (CDCH) Discussion Board

Advanced search  

News:

Pages: [1] 2 3   Go Down

Author Topic: LDM MINE SHAFT PROJECT  (Read 1998 times)

Mike Gold

  • Guest
LDM MINE SHAFT PROJECT
« on: February 18, 2010, 07:47:57 AM »

SHAREHOLDER UPDATE
LAS DOS MARIAS

October 20, 2009

Dear Medinah Shareholders:
Medinah Mining (Chile) is the owner of the Las dos Marias claims 1-30, encompassing 130 hectares in total area, and geographically located on the headwaters of Quebrada Durazno river on the northwest slope of the Alto de Lipangue plateau. Further, it lies approximately three (3) kilometers from the highly impressive breccia discoveries on the Gordon claims.

Exploration was carried out under the supervision of A.C.A. Howe International, Gordon House P. Geo., and Paul Jones, Mining Engineer with DM 99-02 encountering a significant high-grade gold intercept at the 68-meter depth. Specific assay values are reported as follows:



A.C.A. Howe International re-sampled these sections and reported as follows:


“Note: one extremely high grade, 2 meter interval with individual samples yielding 61.77 and 122.2 grams gold/tonne, respectively was returned from DM 99-02 between 68 and 70 meters. A.C.A. Howe re-assay of the secondary sample in this interval yielded 455 grams gold/tonne across 1 meter, indicating the probable nugget nature of the gold mineralization in this interval.”

Paul Jones, Mining Engineer and P. Geo., prepared a proposal for the development of this area by sinking a vertical shaft to a depth of 80 meters to provide access for new drifts to follow and extract the rich gold value encountered by diamond drilling. His proposal recommended a shaft 2 meters by 3 meters in cross section with one compartment for hosting and a half compartment for service components. Mr. Jones recommended this project when gold was valued at less that $400 an ounce compared to current values exceeding $1,000 an ounce. Based on the increases in commodity economic valuations the project is now deemed prudent and cost effective.

Medinah Mining (Chile), in concert with its partners, will fully finance and commence development of the vertical shaft following the recommendations of Mr. Paul Jones. Startup of this work program will commence during the week of October 19, 2009 that will lead to a production operation.

This is the first operational/developmental plan for the Alto de Lipangue area and the quickest to feasibly undertake. Other more extensive programs, with Joint Venture partners, to fully develop the Gold, Copper, Molybdenum, and Silver metals at Alto de Lipangue will continue to be worked on toward the ultimate goal of completion.

Medinah Mining (Chile) is the 100% owner of the Las dos Marias claims, 1-30 and Medinah Minerals, Inc. (USA) retains a 50% interest in the ownership of Medinah Minerals (Chile).

Juan Jose Quijano, President/CEO/Director
Medinah Minerals, Inc. USA
Medinah Mining, Chile


 
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #1 on: February 18, 2010, 07:48:44 AM »

MEDINAH MINERALS INC.
Shareholder Update – December 2009
Dear Medinah Shareholders:

As President/CEO of Medinah Minerals, Inc. I report the 2009 year has been very busy advancing the projects of the Company, acquiring new production opportunities, and examining numerous proposals for a Joint Venture on the Alto de LiPangue property.

The completion of a meaningful and long term agreement has taken far more time than anyone would have anticipated, but Management wants to ensure that the right partners are chosen for the future of this project and that they share the same goals and principles. Numerous proposals for Joint Venture participation on Alto de LiPangue project were reviewed. Many trips to the property with mining professionals and principals involved extensive documentation passing to legal parties for consideration. The parties that Management has continued to negotiate have established a close relationship and meet the business goals criteria for a long term working partnership. I feel that a realistic decision is finally close.

Medinah acquired a 15% interest in the Polo claims, located south of Santiago, Chile. The preliminary indications are that this will be a very worthwhile project. Professional mining crews are at site and preparing status reports for our shareholders.

Significant progress is underway at the company’s 5% holding at the Pumillahue placer operation. The first shaft has been completed and the second of a total of six planned shafts is now within 9 meters of completion. The production plant is operational and testing of the various materials continues with the goal of full production as more material becomes available.

Equipment is being transported weekly to the Las dos Marias property near the Alto de LiPangue to ready the sinking of a shaft. Road improvements are also being done to reduce travel distance from 30 to 17 kilometers for transport of captured materials.
On behalf of Medinah Minerals, Inc.’s Management and Board of Directors, I take this opportunity to extend the best of the Holiday Season to everyone and look forward to meeting all shareholders in the New Year.

Sincerely,

 

Juan José Quijano Fernández
President/CEO, Medinah Minerals, Inc
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #2 on: February 18, 2010, 07:50:54 AM »

Geology Map and drawing showing proposed mine shafts.
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #3 on: February 18, 2010, 07:52:16 AM »

5  The Mining Play Forums / Topics / Re: Medinah Minerals and Cerro Dorado - The Main Discussion

Some of us have been digging around to ascertain the nature of the delays at LDM.  The plan there is a vertical shaft down to the good stuff residing between 68 and 70-meters where ACA Howe found 454 grams per tonne gold. I think there are 3 decent looking zones on the way down to the high grade goodies. From the base of this shaft an adit (tunnel) is going to plunge yet deeper at a certain angle and out of the side of the mountain.  This is the “production shaft” through which the ore will be brought out of the mountain.  This shaft also drains out any water encountered from the water table.  As I understand it the vertical shaft is for ventilation and emergency escape/access.  I’m assuming the recent roadwork done to decrease the travel distance to the production facility by 13 Km was done near the exit of the adit from the mountain.  Apparently the original battle plan was inked and then an engineer suggested to steepen the angle of the production adit.  This increased the length of the adit by 42 meters.  I assume this change needed to be papered- over in a revised contract and it probably cost a few extra bucks to go with plan B.  I’m not sure if the environmental guys have to sign off on the revised contract or not.  Apparently the environmental issues at Madre de Dios (Pumillahue) were significant for Bruce Turner and the other partners in that agriculture and fishing were involved.  At LDM the creek the water table water will drain into (Quebrada Durazno) is dry 9 months of the year and there is no fishing or agriculture in the area.  There is so much artisanal mining in that area that it sounds like the environmental issues are pretty much “grandfathered in”.  The other thing we found out from the old Ernst and Young title report handed out at several of the AGMs years ago is that is that the overall Lipangue property complex sits in 2 different mining “districts” and mining “provinces”.  The western part of the plateau is in the District of Curacavi and the Province of Chacabuco and the eastern part is in the Lampa District and the Province of Melpilla.   The “Region” we’re in is the “Metropolitan Region of Santiago” FWIW.
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #4 on: February 18, 2010, 07:52:58 AM »

REVISED TO INCLUDE THE REST OF THE SHAFT. I MAY UPDATE THIS LATER TO REFLECT NEW DETAILS AS THEY BECOME AVAILABLE.

So, when the news comes out that that the LDM mine shaft has started..what then? What should we expect as we head down the shaft on a daily basis?  Based on the limited information that is known about the LDM project, the ACA Howe report, and some knowledge about mine shafts in general, I have attempted to determine just that. Enjoy!!!  Please note:  The schedule does not take into account weekends, holidays, parties, siestas, equipment breakdowns, union/labor troubles, road problems, flash floods, ground water issues, or any other unforeseen problem! 

Day 1.  We reach a depth of 3 meters and have removed 28 cubic meters of rock weighing about 75.6 tons.  All of this material is discarded as it is simply overburden, regolith, and boulders.

Day 2.   Depth completed to 6 meters. Material discarded.

Day 3.  Depth completed to 9 meters.  Material discarded.

Day 4.  Depth completed to 12 meters.  Starting at 10 meters, we will encounter 20% disseminated pyrite and strong epidote alteration.  Gold values average around 1.7 grams gold/tonne.  This works out to about 3 ounces of Gold removed!  The first 40 meters or so down, in general they will encounter a variably sheared and quartz-carbonate-pyrite veined pyritic siliceous volcanic unit. I would expect all of this material to be placed in the low grade gold pile on the surface

Day 5.  Depth completed to 15 meters.  About 4.5 ounces of gold mined!

Day 6.  Depth completed to 18 meters.  Same amount of gold.

Day 7 through Day 13 about the same as previous.

Starting about Day 13, things get a little more interesting.   We will reach a depth of 39 meters.  At 37 meters of depth, this will correspond to an increase in disseminated pyrite content in the volcanic unit along with strong epidote-diopside-chlorite alteration.  Gold values increase to 2.44 grams per tonne.  We have finally entered the “shear zone”!

On Day 14, we reach a depth of 42 meters.  Several quartz-carbonate pyrite veinlets and stringers will be seen. Gold values increase to 9 grams/tonne.  There is a 2 meter wide fault zone that will be encountered between 40 and 42 meters.  The miners might consider making a cross-cut drift to follow the gold at this level.  Expect this material to be placed in the medium grade gold pile on the surface.

From Day 15 to Day 22 when we will reach a depth of 66 meters-the amount of gold that will be encountered on those days is uncertain since there was no assays taken by Gordon House when it was originally drilled. However, based on remarks from Robert, I believe it will be similar to the 1.7 grams gold/tonne encountered earlier.  If you add up all the gold encountered thus far..it would amount to about 100 ounces or about $100,000 worth.

Day 23.  The big day!!!! With all the excitement, the miners dig extra hard/long and reach a depth of 73 meters  At 66 meters, a significant fault/breccia gouge zone will be intersected and continue to a depth of 73 meters. Bonanza grade gold will be encountered.  The exact grade that will be found is unknown as core recovery was extremely poor but as high as 455 grams gold/tonne despite the poor recovery was encountered during the previous drilling.  I have decided to assume a conservative 75 grams gold/tonne over the interval of 66 to 73 meters.  About 425 ounces or about $425,000 is recovered and placed in the high grade gold pile at the surface.  All of this will be immediately placed on a truck and sent directly to Enami for processing.

Day 24.  Now what? Do the miners linger at this level or do they proceed with completion of the planned 100 meter vertical shaft?  (Note: Miners generally design the vertical shaft to the maximum depth of any expected future workings.) I assume that the horizontal adit will be worked on simultaneously as the vertical shaft. Working on a horizontal adit is easier to do so development of it will exceed that of a vertical shaft.  However, the length of it is much longer so it will lag that of the vertical shaft.  It doesn’t much sense to complete the vertical shaft well ahead of the adit-the optimum being at the same time.  I estimate that the miners have two weeks to kill so they might as well make the best of it! The next thing to consider is the orientation of the vein relative to the vertical shaft.  It appears that vein plunges steeply down(and up towards the surface) with about a 30 degree offset from vertical.  The miners would likely test both directions. If we assume that stay in the 75 grams gold/tonne material, this will indeed be exciting couple of weeks for Medinah!  Each day, they could be pulling out around 200 ounces per day of material.  By day 38, another $2.8 million of gold has been extracted.  There is now no doubt about it..the LDM project is a success!

Day 39.  With the adit quickly moving forward, the miners on the vertical shaft regretfully leave behind the pay zone and work toward completing the rest of their shaft.  Below the fault zone between 70 and 80 meters, the miners will encounter bleached breccia and andesite with numerous quartz-carbonate-pyrite-chalcopyrite veinlets and factures.  They will then go through a thick sequence of porphyritic andesite with varying amounts of silicification and fine disseminated pyrite along with quartz-carbonate-pyrite and arsenopyrite-chalcopyrite veinlets. Overall, the gold grade will be low.  By Day 50, the vertical shaft is complete and miners from the adit and the shaft are able to shake hands through a hole congratulating themselves on a job well done!  With the shafts complete, the next month or so will involve completing all the necessary utilities, airflow, material handling, safety issues and like.  Beyond that, the miners will go back to the 70 meter level to complete the workings there until that vein is exhausted. Other veins will be targeted as discovered.  In particular, the hanging wall of the shear zone near the footwall interface will be high value target.  Simultaneously to all of this, one can assume that surface exploration will be on-going such as more IP survey’s and drilling to identify further targets to be exploited.  New shafts will be sunk further to the North in the shear zone..with lateral drifts heading back to the South to hook up with the exiting new workings.  By the time, all of this taking place, I suspect Medinah will have already been bought out due to a sucessful JV at Lipangue. Either way, it will be exciting/interesting to follow as the project goes forward.  Cheers!
« Last Edit: February 18, 2010, 10:10:06 AM by admin »
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #5 on: February 18, 2010, 08:01:56 AM »

Other Diagrams:

Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #6 on: February 18, 2010, 08:02:56 AM »

Another Geology Map.
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #7 on: February 18, 2010, 08:06:10 AM »

Logged

geoly37

  • Hero Member
  • *****
  • Posts: 1,297
  • COME ON ALREADY!!!
Re: LDM MINE SHAFT PROJECT
« Reply #8 on: February 18, 2010, 12:14:46 PM »

mike has taken it upon himself to show his readers what a typical operation would look like.  there has been some correct info and some speculation put into his projections but there has been no changes in the plans of jj.
----- Original Message -----
As per LES
Logged
heyyyyyy KOOOOOL-AIDDDD!

funnyman

  • Sr. Member
  • ****
  • Posts: 447
Re: LDM MINE SHAFT PROJECT
« Reply #9 on: February 18, 2010, 12:18:11 PM »

mike has taken it upon himself to show his readers what a typical operation would look like.  there has been some correct info and some speculation put into his projections but there has been no changes in the plans of jj.
----- Original Message -----
As per LES

Can somebody remind me if we have been told who is financing this shaft?
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #10 on: February 18, 2010, 12:46:42 PM »

A MP exclusive..see attached old report on the Los Dos Marias found nowhere else..not even Medinah's own website.

« Last Edit: February 18, 2010, 01:09:49 PM by Mike Gold »
Logged

funnyman

  • Sr. Member
  • ****
  • Posts: 447
Re: LDM MINE SHAFT PROJECT
« Reply #11 on: February 18, 2010, 02:13:16 PM »

A MP exclusive..see attached old report on the Los Dos Marias found nowhere else..not even Medinah's own website.

Thanks Mike but who are the referred to partners? Are we entitled to know?
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #12 on: February 18, 2010, 02:19:41 PM »

A MP exclusive..see attached old report on the Los Dos Marias found nowhere else..not even Medinah's own website.

Thanks Mike but who are the referred to partners? Are we entitled to know?

Knowing who the partners are..is on a need to know basis only..apparantly we don't need to know as we don't know!  8)
Logged

funnyman

  • Sr. Member
  • ****
  • Posts: 447
Re: LDM MINE SHAFT PROJECT
« Reply #13 on: February 18, 2010, 02:55:52 PM »

A MP exclusive..see attached old report on the Los Dos Marias found nowhere else..not even Medinah's own website.

Thanks Mike but who are the referred to partners? Are we entitled to know?


OK, so has the progress of the shaft been released, how many meters deep is the shaft at this time?

Knowing who the partners are..is on a need to know basis only..apparantly we don't need to know as we don't know!  8)
Logged

Mike Gold

  • Guest
Re: LDM MINE SHAFT PROJECT
« Reply #14 on: February 18, 2010, 03:15:21 PM »

A MP exclusive..see attached old report on the Los Dos Marias found nowhere else..not even Medinah's own website.

Thanks Mike but who are the referred to partners? Are we entitled to know?


OK, so has the progress of the shaft been released, how many meters deep is the shaft at this time?

Knowing who the partners are..is on a need to know basis only..apparantly we don't need to know as we don't know!  8)

I have not heard that they have started actual construction of the vertical shaft or the adit. When they do, I assume we will hear about within a day or two.
Logged
Pages: [1] 2 3   Go Up